Works on the new Mordi Aquatic Centre are progressing well and remain on track for completion in late-2026. 

Recently completed works

  • Roofing complete across the centre 
  • Huge 150kl rainwater harvesting tank installed for sustainable toilet flushing, irrigation and pool top-up   
  • Pool hall change rooms taking shape with walls in, plastered and painted   
  • Installation of a large underground tank to help manage and treat stormwater. 

Works underway and upcoming

  • Scaffolding going up in the pool hall as we get ready to sand and finish the timber beams  
  • Concrete being poured across the pool concourses 
  • Waterproofing works in the change rooms  
  • Internal services fitout continues with running of electrical cables throughout the building and connecting pool plant and equipment 
  • Walls going up in the reception and café areas 
  • Painting in the Level 1 gym and group fitness spaces.  

Membership update 